Ajmera Developers

Company or firm · 3 projects · 4 MahaRERA registrations

Projects34 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rajhans Kshitij, Aspen, Wing CP99000006700Vasaivirar City (M Corp)2017Not reported31 Dec 2018—On date
Vishwa NagriP99000022924Vasaivirar City (M Corp)2019Not reported30 Mar 2022—On date
Vishwa NagriP99000024662Vasaivirar City (M Corp)2020Not reported30 Mar 2023—On date
Vishwa Nagri Building No. 1P99000034620Vasaivirar City (M Corp)2022Not reported30 Sep 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rajhans Kshitij, Aspen, Wing COn date
  • Vishwa NagriOn date
  • Vishwa NagriOn date
  • Vishwa Nagri Building No. 1On date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology