Ajit Girdharilal Nahar

Individual promoter · 5 projects · 5 MahaRERA registrations

Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
GiripushpP52100002063Pune (M Corp.)2017Not reported30 Dec 2021—On date
Green CityP52100002420Shivne (Part)2017Not reported30 Dec 2021—On date
PeriwinkleP52100017310Wagholi2018Not reported30 Dec 2024—On date
Green City Phase II K BuildingP52100026930Shivne (Part)2020Not reported30 Jun 202430 Jun 2025+12 months
Green City Phase II J BuildingPC1260002602123Shivne (Part)2026Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • GiripushpOn date
  • Green CityOn date
  • PeriwinkleOn date
  • Green City Phase II K Building+12 mo
  • Green City Phase II J BuildingOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Green City Phase II K Building (P52100026930).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology