Agile Real Estate Dev Private Limited
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 1 extended
3Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| PrimeraP51700055574 | Thane (M Corp.) | 2024 | Active | 31 Dec 2029 | — | On date |
| Sector B- Tower A and BPR1332022500106 | Thane (M Corp.) | 2025 | Certificate Signed | 31 Dec 2031 | 31 Dec 2031 | On date |
| Estella - Tower C and DPR1331012600027 | Balkum | 2026 | Certificate Signed | 30 Jun 2032 | 30 Oct 2032 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Estella - Tower C and D (PR1331012600027).
Regulatory cases across projects
- complaintComplaint CC12501489 · Primera · P51700055574
- complaintComplaint CC12501551 · Primera · P51700055574
- complaintComplaint CC12502352 · Primera · P51700055574
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology