Adityaraj Builders
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date4 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai PrasadP51800004104 | Kurla | 2017 | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 months |
| Suyog ChsP51800004742 | Kurla | 2017 | Certificate Signed | 28 Feb 2021 | 30 Jun 2022 | +16 months |
| Manoranjan ChsP51800022235 | Kurla | 2019 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Adityaraj AvenueP51800024409 | Kurla | 2020 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Adityaraj BreezeP51800029546 | Kurla | 2021 | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Shivraj Chs Adityaraj ShivrajP51800045791 | Kurla | 2022 | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Shraddha Chs Adityaraj AnchorP51800051334 | Vikhroli | 2023 | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Sai Prasad (P51800004104).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology