Adityaraj Builders

Company or firm · 7 projects · 7 MahaRERA registrations

7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date4 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai PrasadP51800004104Kurla2017Certificate Signed30 Jun 202130 Dec 2022+18 months
Suyog ChsP51800004742Kurla2017Certificate Signed28 Feb 202130 Jun 2022+16 months
Manoranjan ChsP51800022235Kurla2019Certificate Signed30 Dec 202330 Dec 2023On date
Adityaraj AvenueP51800024409Kurla2020Certificate Signed30 Dec 202430 Dec 2024On date
Adityaraj BreezeP51800029546Kurla2021Certificate Signed31 Dec 202431 Dec 2024On date
Shivraj Chs Adityaraj ShivrajP51800045791Kurla2022Certificate Signed31 Mar 202631 Mar 2026On date
Shraddha Chs Adityaraj AnchorP51800051334Vikhroli2023Certificate Signed31 Mar 202731 Jul 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Prasad+18 mo
  • Suyog Chs+16 mo
  • Manoranjan ChsOn date
  • Adityaraj AvenueOn date
  • Adityaraj BreezeOn date
  • Shivraj Chs Adityaraj ShivrajOn date
  • Shraddha Chs Adityaraj Anchor+4 mo

Track record notes

  • 4 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Sai Prasad (P51800004104).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology