Aditya Developers
Company or firm · 6 projects · 6 MahaRERA registrations
Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%6 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Laxmi ChsP51800007179 | Borivali | 2017 | Not reported | 18 Jan 2021 | — | On date |
| Dahisar Snehal ChsP51800007224 | Borivali | 2017 | Not reported | 12 Feb 2020 | — | On date |
| New Ekta ChsP51800007346 | Borivali | 2017 | Not reported | 30 Dec 2021 | — | On date |
| Urvashi ChsP51800008896 | Borivali | 2017 | Not reported | 16 Mar 2021 | — | On date |
| Ankit ChsP51800008898 | Borivali | 2017 | Not reported | 25 Dec 2019 | — | On date |
| Borivali Gulmohar Terrace ChsP51800011229 | Borivali | 2017 | Not reported | 25 Dec 2019 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 6 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology