Company or firm · 7 projects · 7 MahaRERA registrations

Projects77 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Alibag HorizonP52000019811Chendhre2019Not reported28 Feb 2023—On date
Alibag SkyvistasP52000033126Alibag2022Not reported31 Dec 2027—On date
Alibag WestendP52000033695Varasoli2022Not reported31 Dec 2027—On date
Alibag ParadiseP52000033789Chendhre2022Not reported31 Dec 2027—On date
ParadiseP51800048380Andheri2023Not reported31 Dec 2027—On date
Alibag BlissP52000050498Chendhre2023Not reported31 Dec 2029—On date
Alibag NirvanaP52000053112Chendhre2023Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Alibag HorizonOn date
  • Alibag SkyvistasOn date
  • Alibag WestendOn date
  • Alibag ParadiseOn date
  • ParadiseOn date
  • Alibag BlissOn date
  • Alibag NirvanaOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.