Ace Properties
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ace AvenueP51800033494 | Kurla | 2022 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Ace AmbienceP51800034328 | Kurla | 2022 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Ace FlorenceP51800034518 | Kurla | 2022 | Certificate Signed | 31 Aug 2024 | 31 Aug 2024 | On date |
| Ace InfiniaP51800051062 | Mulund | 2023 | Not reported | 31 Dec 2025 | — | On date |
| Ace MarvelPM1180002500766 | Mulund | 2025 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Ace Marvel (PM1180002500766).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology