Abid Khan

Individual promoter · 1 project · 1 MahaRERA registration

Also appears as Abid Khan

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
1 Emarz TowerP50500078924Nagpur (M Corp.)2025Certificate Signed28 Feb 202728 Jun 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 1 Emarz Tower+4 mo

Track record notes

  • Longest extension on record: 4 months, for 1 Emarz Tower (P50500078924).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology