Abhijit Prakash Borase
Individual promoter · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai BlessingsP52100013716 | Pimpri Chinchawad (M Corp.) | 2017 | Not reported | 31 Dec 2019 | 30 Jun 2022 | +30 months |
| Sai AasraP52100026893 | Tathwade | 2020 | Not reported | 20 Apr 2023 | — | On date |
| Sai VivekP52100027160 | Pimpri Chinchawad (M Corp.) | 2020 | Not reported | 25 Apr 2024 | — | On date |
| Sai AaravP52100048212 | Tathwade | 2022 | Not reported | 31 Jul 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 30 months, for Sai Blessings (P52100013716).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology