Abhay Sharad Walawalkar
Individual promoter · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mohan ResidencyP52900005042 | Kudal (Ct) | 2017 | Certificate Signed | 30 Nov 2020 | 30 Nov 2020 | On date |
| Usha Bhaskar ResidencyP52900028654 | Kudal (Ct) | 2021 | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| AlaukikP52900079082 | Kudal (Ct) | 2025 | Certificate Signed | 31 May 2029 | 30 Sep 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Alaukik (P52900079082).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology