Abhay Sharad Walawalkar

Individual promoter · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mohan ResidencyP52900005042Kudal (Ct)2017Certificate Signed30 Nov 202030 Nov 2020On date
Usha Bhaskar ResidencyP52900028654Kudal (Ct)2021Certificate Signed30 Sep 202530 Sep 2025On date
AlaukikP52900079082Kudal (Ct)2025Certificate Signed31 May 202930 Sep 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mohan ResidencyOn date
  • Usha Bhaskar ResidencyOn date
  • Alaukik+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Alaukik (P52900079082).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology