Aayush Developers

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aayush PoornimaP51800002056Kurla2017Not reported30 Jun 201929 Dec 2020+18 months
Aayush AarnaP51800027442Kurla2020Not reported30 Jun 2023—On date
Aayush AyaanshP51800051964Chembur2023Not reported31 Dec 2025—On date
Aayush GokulP51800079889Chembur2025Not reported30 Jun 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aayush Poornima+18 mo
  • Aayush AarnaOn date
  • Aayush AyaanshOn date
  • Aayush GokulOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Aayush Poornima (P51800002056).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology