Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sandhyarang ApartmentsP50500033288Nagpur (M Corp.)2022Not reported31 Dec 202230 Jun 2023+6 months
Vasunandan ApartmentsP50500048072Nagpur (M Corp.)2022Not reported31 Dec 2024—On date
Shantipurush ApartmentP50500053661Nagpur (M Corp.)2023Not reported31 Mar 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sandhyarang Apartments+6 mo
  • Vasunandan ApartmentsOn date
  • Shantipurush ApartmentOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 6 months, for Sandhyarang Apartments (P50500033288).

Regulatory cases across projects