Aarti Estates
Company or firm · 4 projects · 4 MahaRERA registrations
Also appears as Bhavya Developer
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| AnthuriumP51700002317 | Thane (M Corp.) | 2017 | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| Navnath ApartmentP51900012813 | Ward Fsouth | 2017 | Certificate Signed | 4 Jul 2019 | 4 Jul 2019 | On date |
| Ace HomesP51700016575 | Thane (M Corp.) | 2018 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Ace ParksideP51700052890 | Thane (M Corp.) | 2023 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Ace Parkside (P51700052890).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology