Skip to content
Deedo home
Menu

Aarav Group

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Subhash Residency Wing C And DP51700048150Kalyan2022Not reported31 Dec 2026—On date
Subhash ResidencyP51700079631Kalyandombivali (M Corp.)2025Not reported31 Mar 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Subhash Residency Wing C And DOn date
  • Subhash ResidencyOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology