Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aaditya Premium 3 Phase 1P50500013254Takali2017Certificate Signed31 Aug 201831 Aug 2019+12 months
Aaditya Premium III Phase 2P50500015877Takli2018Certificate Signed17 Mar 201917 Mar 2019On date
Aaditya Glory IIP50500017511Nagpur (Rural)2018Certificate Signed5 Feb 20214 Aug 2022+18 months
Aaditya Premium 5P50500023628Takali2019Certificate Signed30 Sep 202330 Sep 2023On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aaditya Premium 3 Phase 1+12 mo
  • Aaditya Premium III Phase 2On date
  • Aaditya Glory II+18 mo
  • Aaditya Premium 5On date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Aaditya Glory II (P50500017511).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology