Aaditya Infrastructures
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Aaditya Premium 3 Phase 1P50500013254 | Takali | 2017 | Certificate Signed | 31 Aug 2018 | 31 Aug 2019 | +12 months |
| Aaditya Premium III Phase 2P50500015877 | Takli | 2018 | Certificate Signed | 17 Mar 2019 | 17 Mar 2019 | On date |
| Aaditya Glory IIP50500017511 | Nagpur (Rural) | 2018 | Certificate Signed | 5 Feb 2021 | 4 Aug 2022 | +18 months |
| Aaditya Premium 5P50500023628 | Takali | 2019 | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Aaditya Glory II (P50500017511).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology