Aadinath Properties

Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed

Also appears as M/S AADINATH PROPERTIES

Projects33 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aadinath ResidencyP51500015645Aurangabad (M Corp.)2018Not reported30 Mar 2023—On date
Aadinath PearlsP51500022014Aurangabad (M Corp.)2019Not reported28 Aug 2025—On date
Aadinath ManakP51500033374Aurangabad (M Corp.)2022Completed31 Jan 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aadinath ResidencyOn date
  • Aadinath PearlsOn date
  • Aadinath ManakOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology