A Square Buildcon
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Janki ResidencyP52100013213 | Talegaon Dabhade (R) | 2017 | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Janki HeightsP52100016789 | Talegaon Dabhade (R) | 2018 | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Janki PrideP52100030705 | Talegaon Dabhade (R) | 2021 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Sai KrupaP52100033101 | Talegaon Dabhade (R) | 2022 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| SwapnpurtiP52100079491 | Talegaon Dabhade (R) | 2025 | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Swapnpurti (P52100079491).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.