A R Constructions

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AlaknandaP52000001200Rodpali2017Certificate Signed31 Jul 201831 Jul 2019+12 months
PushpakP52000001781Karanjade2017Certificate Signed30 Apr 201830 Apr 2018On date
IndraprasthaP52000001877Karanjade2017Certificate Signed30 Jun 201929 Dec 2020+18 months
VrundavanP52000023802Taloja2020Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Alaknanda+12 mo
  • PushpakOn date
  • Indraprastha+18 mo
  • Vrundavan+4 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Indraprastha (P52000001877).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology