A Plus Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Golden Vann - Phase 4P52000003205Ardhe2017Not reported24 Sep 2022—On date
Golden VanP52000020754Ardhe2019Not reported30 Mar 202528 Feb 2026+11 months
Shrusti VanP52000021325Ardhe2019Not reported30 Mar 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Golden Vann - Phase 4On date
  • Golden Van+11 mo
  • Shrusti VanOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 11 months, for Golden Van (P52000020754).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology