A K Constructions

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+21 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Westwood Estates Phase IP52100004285Mulshi2017Not reported30 Dec 202130 Jun 2024+30 months
Westwood Estates Phase IIP52100019780Wakad2019Not reported30 Jun 202328 Jun 2024+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Westwood Estates Phase I+30 mo
  • Westwood Estates Phase II+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Westwood Estates Phase I (P52100004285).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology