A K Constructions
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+21 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Westwood Estates Phase IP52100004285 | Mulshi | 2017 | Not reported | 30 Dec 2021 | 30 Jun 2024 | +30 months |
| Westwood Estates Phase IIP52100019780 | Wakad | 2019 | Not reported | 30 Jun 2023 | 28 Jun 2024 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 30 months, for Westwood Estates Phase I (P52100004285).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: WESTWOOD ESTATES PHASE I (Regulatory Case No. 42 of 2023) dated 18 August 2023. · Westwood Estates Phase I · P52100004285 · 22 Aug 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology