A. B. Builders
Company or firm · 2 projects · 2 MahaRERA registrations
Also appears as M/S. A. B. BUILDERS
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases2MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Suresh ApartmentsP50500025773 | Nagpur (M Corp.) | 2020 | Not reported | 28 Feb 2023 | — | On date |
| Chirag ApartmentP50500033766 | Nagpur (M Corp.) | 2022 | Not reported | 31 Dec 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- DeregisteredDeregistered: CHIRAG APARTMENT · Chirag Apartment · P50500033766
- DeregisteredDeregistered: SURESH APARTMENTS · Suresh Apartments · P50500025773
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology