Skip to content

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Zadgaon Ct · Ratnagiri
Registration
RERA numbers
PromoterKedar Constructions
Status on MahaRERACertificate Signed
Registered on27 Mar 2026
Delivery
Promised completion15 Jun 2027
Revised completion15 Oct 2027
Delay vs RERA date+4 monthsrevised completion date
Extension certificates0
Size
Project land area—
Buildings on record1
Units19
Units booked—
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA15 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology