Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Gondhalpada · Raigarh
Registration
RERA numbers
PromoterForstar D B Realty
Status on MahaRERACertificate Signed
Registered on25 Jun 2025
Delivery
Promised completion20 Feb 2030
Revised completion20 Jun 2030
Delay vs RERA date+4 monthsrevised completion date
Extension certificates0
Size
Project land area—
Buildings on record14
Units76
Units booked—
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA21 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology