Skip to content

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Kalyan · Maharashtra
Registration
RERA numbers
PromoterVaidikh Nirmaan LLP
Status on MahaRERACertificate Signed
Registered on4 Mar 2024
Delivery
Promised completion30 Nov 2026
Revised completion30 Mar 2027
Delay vs RERA date+4 monthsrevised completion date
Extension certificates0
Size
Project land area—
Buildings on record3
Units314
Units booked19863% of units
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA15 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology