Skip to content
Deedo home
Menu

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Mykhop · Palghar
Registration
RERA numbers
PromoterMsd Shivay Enterprise LLP
Status on MahaRERA—
Registered on30 May 2020
Delivery
Promised completion7 Sep 2022
Revised completion31 Dec 2026
Delay vs RERA date+4 years and 3 monthsrevised completion date
Extension certificates1
Size
Project land area—
Buildings on record—
Units—
Units booked—
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA7 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology