Skip to content
Deedo home
Menu

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Haveli · Maharashtra
Registration
RERA numbers
PromoterVaishnavi Developers
Status on MahaRERACertificate Signed
Registered on2 Jan 2020
Delivery
Promised completion30 Mar 2023
Revised completion30 Sep 2023
Delay vs RERA date+3 years and 6 monthslatest date on record has passed
Extension certificates1
Size
Project land area—
Buildings on record1
Units74
Units booked4865% of units
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA13 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through13 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology