Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Haveli · Maharashtra
Registration
RERA numbers
PromoterSun Properties
Status on MahaRERA—
Registered on16 May 2019
Delivery
Promised completion31 Mar 2022
Revised completion30 Mar 2024
Delay vs RERA date+4 years and 6 monthslatest date on record has passed
Extension certificates1
Size
Project land area—
Buildings on record—
Units—
Units booked—
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA7 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology