Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Mumbai City · Mumbai City
Registration
RERA numbers
PromoterBhurji Developers LLP
Status on MahaRERA—
Registered on5 Jun 2018
Delivery
Promised completion30 Dec 2021
Revised completion31 Mar 2027
Delay vs RERA date+5 years and 3 monthsrevised completion date
Extension certificates1
Size
Project land area—
Buildings on record—
Units—
Units booked—
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA7 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology