Projects compared side by side
Dhule (M Corp.) · Dhule
Registration
RERA numbers
PromoterPiyush Lifespaces Private Limited
Status on MahaRERACompleted
Registered on5 Sep 2019
Delivery
Promised completion30 Dec 2023
Revised completion—
Delay vs RERA dateNoneshown as completed
Extension certificates0
Size
Project land area543 sq m
Buildings on record2
Units16
Units booked—
Regulatory
MahaRERA cases0
Documents on file62
Last checked on MahaRERA8 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology