Neral · Raigarh
Registration
RERA numbers
PromoterRohidas Janardan More
Status on MahaRERACertificate Signed
Registered on14 Aug 2017
Delivery
Promised completion30 Dec 2021
Revised completion31 Dec 2027
Delay vs RERA date+6 yearsrevised completion date
Extension certificates1
Size
Project land area—
Buildings on record1
Units12
Units booked325% of units
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA13 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.