Projects compared side by side
Atgaon · Thane
Registration
RERA numbers
PromoterAghav Developers
Status on MahaRERACertificate Signed
Registered on1 Sep 2017
Delivery
Promised completion1 Jul 2023
Revised completion30 Jul 2027
Delay vs RERA date+4 yearsrevised completion date
Extension certificates1
Size
Project land area—
Buildings on record7
Units114
Units booked—
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA13 Oct 2026