Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Poshir · Raigarh
Registration
RERA numbers
PromoterDove Developers
Status on MahaRERACertificate Signed
Registered on26 Sep 2017
Delivery
Promised completion31 Jul 2023
Revised completion31 Mar 2035
Delay vs RERA date+11 years and 8 monthsrevised completion date
Extension certificates1
Size
Project land area—
Buildings on record44
Units41
Units booked—
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA12 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through12 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology