Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Deolaligaon · Nashik
Registration
RERA numbers
PromoterShri Hari Vaikuntha Co-Op Hsg Soc
Status on MahaRERALapsed
Registered on31 Aug 2017
Delivery
Promised completion30 Jun 2019
Revised completion—
Delay vs RERA date+7 years and 3 monthslatest date on record has passed
Extension certificates0
Size
Project land area561 sq m
Buildings on record1
Units17
Units booked—
Regulatory
MahaRERA cases0
Documents on file16
Last checked on MahaRERA11 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology