Nashik (M Corp.) · Nashik
Registration
RERA numbers
PromoterShree Samarth Builders And Developers
Status on MahaRERACompleted
Registered on22 Aug 2017
Delivery
Promised completion31 Dec 2020
Revised completion30 Jun 2023
Delay vs RERA date+2 years and 5 monthsrevised completion date
Extension certificates1
Size
Project land area637 sq m
Buildings on record2
Units16
Units booked—
Regulatory
MahaRERA cases0
Documents on file33
Last checked on MahaRERA11 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology