Skip to content

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Wadgaon Kolhati (Ct) · Aurangabad
Registration
RERA numbers
PromoterVikas Laxman Chaudhary
Status on MahaRERALapsed
Registered on11 May 2018
Delivery
Promised completion30 Dec 2025
Revised completion—
Delay vs RERA date+9 monthslatest date on record has passed
Extension certificates0
Size
Project land area1,199 sq m
Buildings on record2
Units—
Units booked—
Regulatory
MahaRERA cases0
Documents on file67
Last checked on MahaRERA10 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through10 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology