Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Amravati (M Corp.) · Amravati
Registration
RERA numbers
PromoterM/S S.navin Builders
Status on MahaRERACompleted
Registered on19 Aug 2017
Delivery
Promised completion31 Dec 2018
Revised completion30 Oct 2020
Delay vs RERA date+1 year and 9 monthsrevised completion date
Extension certificates1
Size
Project land area990 sq m
Buildings on record1
Units30
Units booked—
Regulatory
MahaRERA cases0
Documents on file16
Last checked on MahaRERA9 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through9 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology