E6 - A, B Wing · Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, Beed

Ambejogai (M Cl) · RERA P52300049313

3Sanctioned habitable floorsregistration certificate
31 Dec 2025Revised completionpromised 31 Dec 2025

Floors

3 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52300049313 · registered 7 Feb 2023
Promised completion
31 Dec 2025
Revised completion
31 Dec 2025
Sanctioned habitable floors
3
ProjectId
26,649
ProjectName
Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, Beed
TotalUnitCount
34
ProjectBuildingId
1,64,007
BuildingNameNumber
E6 - A, B WING
FsiWithSanctionSqmts
G+2
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
20
ProjectRegistartionNo
P52300049313
ProjectBuildingWingsId
1,67,464
BuildingWingsNameNumber
NA
NonResidentialUnitCount
14
AdvertisedBuildingNameNumber
E6 - A, B WING
NoOfBuildingWingFloorProposed
3
NoOfBuildingWingFloorHabitable
3
NoOfBuildingWingFloorSanctioned
3

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——34not published
Total34
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology