Skip to content

Raaj Swapnapurti Elite

Certificate Signed

Tisgaon, Aurangabad 431136 |Promoter: S Raaj Associates

Residential / Group HousingRERAP51500024516
18 Feb 2020Registered with MahaRERA
30 Dec 2024Promised completion
4Buildings
39Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
4
Unit types
2 BHK ROW HOUSE39 units in all
Address
Gut No 94 Part Tisgaon, Waluj Mahanagar, TisgaonPIN 431136
Designated bank account
7
Developed in phases
Yes

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2024

The latest completion date on record passed 1 year and 10 months ago.

Registered
18 Feb 2020
Promised
30 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150002451618 Feb 202030 Dec 202430 Dec 2024S Raaj AssociatesProject page

4 buildings

Buildings and wings named in the registration

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 39 units booked (0%), as the promoter reported to MahaRERA

2 BHK ROW HOUSE · 39 units
BuildingTypeCarpet areaUnitsBooked
Row House A1 Type2 BHK ROW HOUSE62.72 sq m · 675 sq ft90
Row House A2 Type2 BHK ROW HOUSE62.72 sq m · 675 sq ft80
Row House A3 Type2 BHK ROW HOUSE58.5 sq m · 630 sq ft100
Row House A4 Type2 BHK ROW HOUSE55.9 sq m · 602 sq ft120

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 36 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 27 Jan 2020Source

Legal

  • Declaration Form BAffidavit cum Declaration Form B for Raaj Swapnapurti Phase 2 for RERA.PDF · uploaded 17 Jan 2020Source
  • Legal Title reportSearch Report of Raaj Swapnapurti Phase 2.PDF · uploaded 21 Jan 2020Source
  • OtherCancellation of Development Agreement Raaj Developers.pdf · uploaded 24 Jul 2021Source

Migrated

  • 1 Details of encumbrancesTo Whom It May Concern Letter for Raaj Swapnapurti Phase 2 for RERA.PDF · uploaded 17 Jan 2020Source
  • 1 Copy of Layout Approval (in case of layout)PLAN 1.pdf · uploaded 17 Jan 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentN A Order.pdf · uploaded 17 Jan 2020Source
Show all 37 documentsShow fewer documents

Migrated

  • 2 Building Plan Approval / NA Order for plotted developmentplan 2 compressed.pdf · uploaded 17 Jan 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.PDF · uploaded 17 Jan 2020Source
  • 1 Declaration in FORM BAffidavit cum Declaration Form B for Raaj Swapnapurti Phase 2 for RERA.PDF · uploaded 17 Jan 2020Source
  • 1 Proforma of Allotment letterNO ATS.PDF · uploaded 17 Jan 2020Source
  • 1 Copy of the legal title reportSearch Report of Raaj Swapnapurti Phase 2.PDF · uploaded 21 Jan 2020Source
  • 1 PAN CardPAN.pdf · uploaded 27 Jan 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate for RERA Raaj Developers Phase II.PDF · uploaded 12 Feb 2020Source
  • 2 Proforma of Allotment letteratsdraft.pdf · uploaded 17 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate for Raaj Swapnapurti Elite.pdf · uploaded 24 Jul 2021Source
  • 1 OtherCancellation of Development Agreement Raaj Developers.pdf · uploaded 24 Jul 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate for Raaj Swapnapurti Elite.pdf · uploaded 18 Aug 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects Certificate Raaj Swapnapurti Elite.pdf · uploaded 3 Dec 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engg.pdf · uploaded 3 Dec 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate S Raaj Associates.pdf · uploaded 18 Jan 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate S Raaj Associates.pdf · uploaded 18 Jan 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A Engineers Certificate Quality Assurance Certificate S Raaj Associates.pdf · uploaded 18 Jan 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Architect Certificate S Raaj Associates MArch 2022.pdf · uploaded 13 May 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Engineers Certificate S Raaj Associates march2022.pdf · uploaded 13 May 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM-2A Engineers Certificate for Quality Assurance S Raaj Associates march2022.pdf · uploaded 13 May 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect June 2022.pdf · uploaded 2 Aug 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engg Cert.pdf · uploaded 2 Aug 2022Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A Engg Cert June 2022.pdf · uploaded 2 Aug 2022Source
  • 1 Disclosure of sold/ booked inventorySold Unsold June 2022.pdf · uploaded 2 Aug 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentRaaj Swapnapurti Elite Occupancy Certificate.pdf · uploaded 18 Jul 2023Source

Technical

  • DocumentN A Order.pdf · uploaded 17 Jan 2020Source
  • DocumentPLAN 1.pdf · uploaded 17 Jan 2020Source
  • Documentplan 2 compressed.pdf · uploaded 17 Jan 2020Source

Technical (Architect)

  • DocumentForm 1 Architect June 2022.pdf · uploaded 2 Aug 2022Source

Technical (Engineer)

  • DocumentForm 2 Engg Cert.pdf · uploaded 2 Aug 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tisgaon, Aurangabad taluka

Survey, CTS, gat or plot numbers

GUT NO 94 PART TISGAON

Boundaries

North
Land Of Gut No 94 Tisgaon
South
18 Mtr Wide Road
East
Land Of Gut No 94 Tisgaon
West
Gut No 90 Tisgaon

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMaimona Imran And Associates—
Chartered accountantU S Bakliwal And Co—
EngineerN G Karkhane—
OtherSalim Bhai Hussain Bhai—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology