PMAY U Tisgaon 227 C

Active

Tisgaon, Aurangabad 431102 |Promoter: Unity Developers

Residential / Group HousingRERAP51500080130
29 Apr 2025Registered with MahaRERA
31 Dec 2025Promised completion
9Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Active
Buildings
9
Land area for this project
22,785 sq m (2,45,251 sq ft)
Permissible built-up area
38,002 sq m (4,09,048 sq ft)
Sanctioned built-up area
38,002 sq m (4,09,048 sq ft)
Recreational open space
8,253 sq m (88,832 sq ft)
Planning authority
Chhatrapati Sambhajinagar Municipal Corporation
Address
Gut no. 227/1, Mauje Tisgaon, Gut no. 227/1 part, , Mauje TisgaonPIN 431102
Designated bank account
Indian Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
PMAY U Tisgaon 227 C is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
29 Apr 2025
Promised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150008013029 Apr 202531 Dec 2025—Unity DevelopersProject page

9 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Bldg-A11a129—
Bldg-A13a149—
Bldg-A15a169—
Bldg-A17a189—
Bldg-A1a29—
Bldg-A3a49—
Bldg-A5a69—
Bldg-A7a89—
Bldg-A9a109—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Bldg-A11a12Closed/Covered8300083
Bldg-A11a12Open Space00000
Bldg-A13a14Closed/Covered8300083
Bldg-A13a14Open Space00000
Bldg-A15a16Closed/Covered8300083
Bldg-A15a16Open Space00000
Bldg-A17a18Closed/Covered7700077
Bldg-A17a18Open Space00000
Bldg-A1a2Closed/Covered8300083
Bldg-A1a2Open Space00000
Bldg-A3a4Closed/Covered8300083
Bldg-A3a4Open Space00000
Bldg-A5a6Closed/Covered8300083
Bldg-A5a6Open Space00000
Bldg-A7a8Closed/Covered8300083
Bldg-A7a8Open Space00000
Bldg-A9a10Closed/Covered8300083
Bldg-A9a10Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Bldg-A11a12

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A13a14

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A15a16

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A17a18

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A1a2

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A3a4

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A5a6

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A7a8

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth75%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Bldg-A9a10

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth75%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceAs per Proposed Plan0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

45 documents held by Deedo, 50 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Commencement Certificates / NA Order for plotted developmentCC Upload.pdf · uploaded 6 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Upload.pdf · uploaded 7 Mar 2025View
  • Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 7 Mar 2025View
  • Commencement Certificates / NA Order for plotted developmentGmail - 76 08 SANTION BP POROPSAL 05032025 PMAY.pdf · uploaded 10 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Unity 227-1 Block C.PDF · uploaded 10 Mar 2025View
  • CERSAI details227 C.pdf · uploaded 10 Mar 2025View
  • a Details of encumbrances concerned to FinanceEncumbrances Legal_Finance.pdf · uploaded 13 Mar 2025View
  • b Details of encumbrances concerned to LegalEncumbrances Legal_Finance.pdf · uploaded 13 Mar 2025View
  • Disclosure for secured/unsecured finance availed for the project7 Disclosure for securedunsecured finance availed for the project.PDF · uploaded 13 Mar 2025View
  • Disclosure of sold/ booked inventorySold Unsold Inventory 227 C.pdf · uploaded 13 Mar 2025View
  • CERSAI details5 Cersai Declaration.PDF · uploaded 13 Mar 2025View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 13 Mar 2025View
  • Declaration about all RERA Designated Bank Accounts (Format A)9 Declaration about RERA Designated Bank Accounts for real estate projects.PDF · uploaded 13 Mar 2025View
  • Declaration in FORM BFORM B - Developer New Revised Upload.pdf · uploaded 13 Mar 2025View
  • Deviation Report with respect to Allotment letter3 Deviation Report with respect to Allotment letter.PDF · uploaded 13 Mar 2025View
  • Deviation Report with respect to model copy of Agreement4 Deviation Report with respect to model copy of Agreement.PDF · uploaded 13 Mar 2025View
  • Other – Legal6 Annexure A.pdf · uploaded 13 Mar 2025View
  • Declaration about Commencement Certificate8 Decleration of Commencement Certificate.pdf · uploaded 13 Mar 2025View
  • Copy of the legal title reportRERA SEARCH REPORT GUT NO 227 Tisgaon.pdf · uploaded 24 Mar 2025View
  • Proforma of Agreement for saleNEW AGREEMENT TO SALE.pdf · uploaded 24 Mar 2025View
  • Proforma of Allotment letterNEW ALLOTMENT LETTER.pdf · uploaded 24 Mar 2025View
  • Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B BANK.pdf · uploaded 24 Mar 2025View
  • Other – Technical6 Annexure A.pdf · uploaded 24 Mar 2025View
  • Other – FinanceForm 3 Declaration 227 C.pdf · uploaded 24 Mar 2025View
  • Other – FinanceWorkorder Tisgaon 227-1.pdf · uploaded 24 Mar 2025View
  • Other – TechnicalCC Tisgaon 227C.pdf · uploaded 24 Mar 2025View
  • Other – TechnicalTisgaon 227-1 Workorder.pdf · uploaded 24 Mar 2025View
  • Other – LegalUNITY DEVELOPERS_1.pdf · uploaded 24 Mar 2025View
  • Other – LegalTisgaon 227-1 7-12_C.pdf · uploaded 24 Mar 2025View
  • Copy of Layout Approval (in case of layout)Layout Final Upload.pdf · uploaded 4 Apr 2025View
  • Withdrawal Update Form 1Form 1 227 C.pdf · uploaded 24 Jul 2025View
  • Withdrawal Update Form 2Form 2 227 C.pdf · uploaded 24 Jul 2025View
  • Withdrawal Update Form 1Unity Developers - Tisgaon Gut No 227-1 Block C - Form 1.pdf · uploaded 27 Oct 2025View
  • Withdrawal Update Form 2Unity Developers - Tisgaon Gut No 227-1 Block C - Form 2.pdf · uploaded 27 Oct 2025View
  • Withdrawal Update Form 1Tisgaon Gut No 227 1 C Form 1.PDF · uploaded 20 Jan 2026View
  • Withdrawal Update Form 2Tisgaon Gut No 227 1 C Form 2.PDF · uploaded 20 Jan 2026View
  • Withdrawal Update Form 1Tisgaon 227 C UD Form 1 Signed.PDF · uploaded 12 May 2026View
  • Withdrawal Update Form 2Tisgaon 227 C UD Form 2 Signed.PDF · uploaded 12 May 2026View
  • Withdrawal Update Form 1Tisgaon Gut 227 Block C Form 1.pdf · uploaded 29 Jul 2026View
  • Withdrawal Update Form 2Tisgaon Gut 227 Block C Form 2.pdf · uploaded 29 Jul 2026View

Promoter documents

  • Declaration Form BFORM B - Developer New Revised Upload.pdf · uploaded 13 Mar 2025View
  • Legal Title reportRERA SEARCH REPORT GUT NO 227 Tisgaon.pdf · uploaded 24 Mar 2025View

Technical documents

  • Layout ApprovalLayout Final Upload.pdfView
  • Building Plan ApprovalBuilding Plan.pdfView

Other legal documents

  • Other – Legal6 Annexure A.pdfView
  • Other – LegalUNITY DEVELOPERS_1.pdfView
  • Other – LegalTisgaon 227-1 7-12_C.pdfView

Financial documents

  • Other – FinanceForm 3 Declaration 227 C.pdf · uploaded 24 Mar 2025View
  • Other – FinanceWorkorder Tisgaon 227-1.pdf · uploaded 24 Mar 2025View

Proforma allotment letter

  • Proforma allotment letterNEW ALLOTMENT LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tisgaon, Aurangabad taluka

Survey, CTS, gat or plot numbers

Gut no. 227/1

As published on MahaRERA's project page

Gut no. 227/1, Mauje Tisgaon

Boundaries

North
Gut no 227 part
South
Open Space
East
60 Mtr Wide Road
West
Canal

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr. Swapnil Shroff—
Chartered accountantCA Yash Nagar—
Chartered accountantSonawane Sahane & Associates—
EngineerSurve Samarth Chandrakant—

Source: MahaRERA project page. Contact details are not shown.