Amrut Sai Kalpavruksha

Completed

Tisgaon, Aurangabad 431102 |Promoter: Amrut Developers

Residential / Group HousingRERAP51500008665
19 Aug 2017Registered with MahaRERA
31 Jul 2018Promised completion
2Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
2
Land area for this project
2,746 sq m (29,554 sq ft)
Permissible built-up area
2,723 sq m (29,314 sq ft)
Sanctioned built-up area
2,723 sq m (29,314 sq ft)
Address
Plot No 65 to 71, Waluj Road, Near Golwadi Chowk, Near A S ClubPIN 431102
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.84853, 75.26378
Amrut Sai Kalpavruksha is at latitude 19.84853, longitude 75.26378.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Jul 2018

The latest completion date on record passed 8 years and 3 months ago.

Registered
19 Aug 2017
Promised
31 Jul 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000866519 Aug 201731 Jul 2018—Amrut DevelopersProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Amrut Sai Kalpavruksha Ph 15—
Amrut Sai Kalpavruksha Ph 25—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Amrut Sai Kalpavruksha Ph 1Closed/Covered000025
Amrut Sai Kalpavruksha Ph 1Open Space00000
Amrut Sai Kalpavruksha Ph 2Closed/Covered000020
Amrut Sai Kalpavruksha Ph 2Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Amrut Sai Kalpavruksha Ph 1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Amrut Sai Kalpavruksha Ph 2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)IN PROGRESS95%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingIN PROGRESS80%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingIN PROGRESS80%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

23 documents held by Deedo, 26 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title reportTitle Report Kalpavruksha.pdf · uploaded 8 Aug 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 8 Aug 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 8 Aug 2017View
  • Copy of Layout Approval (in case of layout)Layout Ph 1_2.pdf · uploaded 9 Aug 2017View
  • Building Plan Approval (IOD)Building Approval Ph 1_2.pdf · uploaded 9 Aug 2017View
  • Declaration in FORM BForm B.pdf · uploaded 10 Aug 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer_certificate.pdf · uploaded 10 Aug 2017View
  • Details of encumbrancesDetails of Encumbrances.pdf · uploaded 10 Aug 2017View
  • Proforma of Allotment letterProforma ATS AL_Ph 1.pdf · uploaded 10 Aug 2017View
  • Proforma of Allotment letterProforma ATS AL_Ph 2.pdf · uploaded 10 Aug 2017View
  • OtherCompletion certificate-compressed.pdf · uploaded 26 Feb 2018View
  • Certificates of Architect (Form 4)Form 4_Kalpvrisha_Architect completion certificate -.pdf · uploaded 26 Mar 2018View
  • Certificates of Architect (Form 4)Form 4_Amrut Kalpvriksha II compressed.pdf · uploaded 21 Jul 2018View
  • OtherCompletion certificate_ Phase II.pdf · uploaded 21 Jul 2018View
  • Certificates of CA (Form 5)FORM 5_Kalpvruksh Scanned.pdf · uploaded 30 Sep 2018View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Amrut sai kalpavruksh ph 1.pdf · uploaded 5 Oct 2018View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Amrut sai kalpavruksh ph 2.pdf · uploaded 5 Oct 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Amrut Dev_Kalpvruksha_Rera Audit Report1819.pdf · uploaded 10 May 2020View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate.pdf · uploaded 24 Jun 2021View

Promoter documents

  • Legal Title reportTitle Report Kalpavruksha.pdf · uploaded 8 Aug 2017View
  • Declaration Form BForm B.pdf · uploaded 10 Aug 2017View

Technical documents

  • Layout ApprovalLayout Ph 1_2.pdfView
  • Building Plan ApprovalBuilding Approval Ph 1_2.pdfView

Other legal documents

  • OtherCompletion certificate-compressed.pdfView
  • OtherCompletion certificate_ Phase II.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma ATS AL_Ph 2.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tisgaon, Aurangabad taluka

Survey, CTS, gat or plot numbers

Plot No 65 to 71

As published on MahaRERA's project page

Plot No 65 to 71

Boundaries

North
Plot No 64
South
15 mtrs wide road
East
Plot No 72 to 77
West
7 mtrs wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGanesh Mharolkar—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology