Shendra Kamangar, Aurangabad 431007 |Promoter: Manish Ramniranjan Agrawal And Amitabh Chaturbhuj Agrawal

9 Mar 2020Registered with MahaRERA
30 Dec 2021Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Completed
Land area for this project
55,076 sq m (5,92,827 sq ft)
Permissible built-up area
81,511 sq m (8,77,376 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
10,415 sq m (1,12,111 sq ft)
Address
198 199 200 201, Jalna Road, Shendra JahangirPIN 431007
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.87542, 75.46334
Sector 41 is at latitude 19.87542, longitude 75.46334.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2021

The latest completion date on record passed 4 years and 10 months ago.

Registered
9 Mar 2020
Promised
30 Dec 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000248649 Mar 202030 Dec 2021—Manish Ramniranjan Agrawal And Amitabh Chaturbhuj AgrawalProject page

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsINTERNAL TRIMIX ROAD WITH FOOTHPATH95%
  • Water SupplyINTERNAL PVC PIPELINE NETWORK ONLY95%
  • Sewerage (Chamber, Lines, Septic Tank , STP)INTERNAL SWR DRAINAGE PIPELINE ONLY95%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree Planting10415.49 SQ.MTR AREA WILL REMAIN AS OPEN SPACE0%
  • Street LightingSTREET LIGHT INSTALLATION AND COMMISSION COMPLETE95%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open Space10415.49 SQ.MTR AREA WILL REMAIN AS OPEN SPACE0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

10 documents held by Deedo, 14 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Details of encumbrancesNO ENC OMICRON.pdf · uploaded 24 Feb 2020View
  • Copy of the legal title reportSEARCH REPORT_compressed.pdf · uploaded 24 Feb 2020View
  • Commencement Certificates / NA Order for plotted developmentNA Order 41.pdf · uploaded 5 Mar 2020View
  • Proforma of Allotment letterNO ATS.pdf · uploaded 5 Mar 2020View
  • Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 5 Mar 2020View
  • Building Plan Approval / NA Order for plotted developmentADTP Letter.pdf · uploaded 5 Mar 2020View
  • Declaration in FORM BForm B Omicron 41.pdf · uploaded 5 Mar 2020View
  • Architect’s Certificate on Completion of Project (Form 4)SECTOR 41 ARCHITECT CERTIFICATE.pdf · uploaded 14 Jul 2020View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNA order.pdf · uploaded 14 Jul 2020View

Promoter documents

  • Legal Title reportSEARCH REPORT_compressed.pdf · uploaded 24 Feb 2020View
  • Declaration Form BForm B Omicron 41.pdf · uploaded 5 Mar 2020View

Technical documents

  • Layout ApprovalLayout Plan.pdfView
  • NA Order for Plotted DevelopmentADTP Letter.pdfView

Proforma allotment letter

  • Proforma allotment letterNO ATS.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Shendra Kamangar, Aurangabad taluka

Survey, CTS, gat or plot numbers

198 199 200 201

As published on MahaRERA's project page

198 199 200 201

Boundaries

North
Gut No 203
South
15 Mtr Road
East
Gut No 197 202
West
Gut No 182 200pt 201 Pt

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrashant Pardeshi—
Chartered accountantPankaj R Mandhane And Company—
EngineerPrashant Pardeshi—