Vardhman Residency

Certificate Signed

Nagar Tisgaon, Aurangabad 431136 |Promoter: K P Ventures

Residential / Group HousingRERAP51500053909
11 Dec 2023Registered with MahaRERA
31 Dec 2028Promised completion
30 Apr 2029Revised completionPushed back 4 months
2Buildings
43Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
Row House, 2BHK, 3BHK, 4BHK43 units in all
Address
Plot No 05 Gut No 105 Part Village Tisgaon Nagar-I Cidco Waluj Mahanagar-I Tq Dist Chhatrapati Sambhaji Nagar, Waluj Mahanagar-1, CidcoPIN 431136
Designated bank account
76
Developed in phases
Yes

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
11 Dec 2023
Promised
31 Dec 2028
Revised
30 Apr 2029

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150005390911 Dec 202331 Dec 202830 Apr 2029K P VenturesProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A Type Building27
B Type Building736

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 43 units booked (0%), as the promoter reported to MahaRERA

Row House · 7 units2BHK · 20 units3BHK · 15 units4BHK · 1 unit
BuildingTypeCarpet areaUnitsBooked
A Type BuildingRow House72.64 sq m · 782 sq ft10
A Type BuildingRow House72.82 sq m · 784 sq ft10
A Type BuildingRow House79.85 sq m · 859 sq ft50
B Type Building2BHK45.39 sq m · 489 sq ft10
B Type Building2BHK46.66 sq m · 502 sq ft10
B Type Building2BHK50.09 sq m · 539 sq ft60
B Type Building2BHK50.85 sq m · 547 sq ft10
B Type Building2BHK51.75 sq m · 557 sq ft50
Show all 15 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B Type Building2BHK54.2 sq m · 583 sq ft50
B Type Building2BHK54.2 sq m · 583 sq ft10
B Type Building3BHK47.26 sq m · 509 sq ft10
B Type Building3BHK59.97 sq m · 646 sq ft40
B Type Building3BHK61.24 sq m · 659 sq ft60
B Type Building3BHK71.43 sq m · 769 sq ft40
B Type Building4BHK82.55 sq m · 889 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 54 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFIRM PAN.pdf · uploaded 23 Oct 2023Source

Legal

  • Legal Title reportSearch Report.pdf · uploaded 23 Oct 2023Source
  • Declaration Form BForm B.pdf · uploaded 23 Oct 2023Source

Migrated

  • 1 PAN CardFIRM PAN.pdf · uploaded 23 Oct 2023Source
  • 1 Copy of the legal title reportSearch Report.pdf · uploaded 23 Oct 2023Source
  • 1 a Details of encumbrances concerned to FinanceNo Eng Fin.pdf · uploaded 23 Oct 2023Source
  • 2 a Details of encumbrances concerned to FinanceNo Eng Legal.pdf · uploaded 23 Oct 2023Source
Show all 55 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalNo Eng Fin.pdf · uploaded 23 Oct 2023Source
  • 2 b Details of encumbrances concerned to LegalNo Eng Legal.pdf · uploaded 23 Oct 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentscan0134_compressed.pdf · uploaded 23 Oct 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentscan0135_compressed (1).pdf · uploaded 23 Oct 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentVardhman CC_compressed.pdf · uploaded 23 Oct 2023Source
  • 1 Declaration about Commencement CertificateKPV - Format-D (Updated).pdf · uploaded 23 Oct 2023Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 23 Oct 2023Source
  • 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 23 Oct 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)VARDHMAN RESIDENCY Form 3.pdf · uploaded 23 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure-A ( Raina Patni ).pdf · uploaded 23 Oct 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure-A ( Praveen Kala ).pdf · uploaded 23 Oct 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsAnnexure-A ( Sanmati Bakliwal ).pdf · uploaded 23 Oct 2023Source
  • 1 Proforma of Allotment letterModal Form of Allotment Letter.pdf · uploaded 23 Oct 2023Source
  • 1 Proforma of Agreement for saleATS Draft RERA.pdf · uploaded 23 Oct 2023Source
  • 1 Deviation Report with respect to Allotment letterAllotment Letter.pdf · uploaded 23 Oct 2023Source
  • 1 Deviation Report with respect to model copy of AgreementAgreement To Sale.pdf · uploaded 23 Oct 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout to be uploaded.pdf · uploaded 24 Oct 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameKP Ventures Format-A.pdf · uploaded 28 Nov 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form-1 Dec 23.pdf · uploaded 22 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Form-1 March 24.pdf · uploaded 22 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Form-1 June 24.pdf · uploaded 22 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Form-1 Sep 24.pdf · uploaded 22 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Form-1 Dec 24.pdf · uploaded 22 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Declaration Dec 23.pdf · uploaded 22 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Declaration March 24.pdf · uploaded 22 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Declaration June 24.pdf · uploaded 22 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Declaration Sep 24.pdf · uploaded 22 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Declartion Dec 24.pdf · uploaded 22 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Dec 23.pdf · uploaded 22 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 March 24.pdf · uploaded 22 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 June 24.pdf · uploaded 22 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 March 24.pdf · uploaded 22 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Sep 24.pdf · uploaded 22 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A 23-24.pdf · uploaded 22 Feb 2025Source

Technical

  • Documentscan0134_compressed.pdf · uploaded 23 Oct 2023Source
  • Documentscan0135_compressed (1).pdf · uploaded 23 Oct 2023Source
  • DocumentLayout to be uploaded.pdf · uploaded 24 Oct 2023Source

Technical (Architect)

  • Document1 Form-1 Dec 23.pdf · uploaded 22 Feb 2025Source
  • Document2 Form-1 March 24.pdf · uploaded 22 Feb 2025Source
  • Document3 Form-1 June 24.pdf · uploaded 22 Feb 2025Source
  • Document4 Form-1 Sep 24.pdf · uploaded 22 Feb 2025Source
  • Document5 Form-1 Dec 24.pdf · uploaded 22 Feb 2025Source

Technical (Engineer)

  • DocumentForm-2 Dec 23.pdf · uploaded 22 Feb 2025Source
  • DocumentForm-2 March 24.pdf · uploaded 22 Feb 2025Source
  • DocumentForm-2 June 24.pdf · uploaded 22 Feb 2025Source
  • DocumentForm-2 March 24.pdf · uploaded 22 Feb 2025Source
  • DocumentForm-2 Sep 24.pdf · uploaded 22 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tisgaon, Aurangabad taluka

Survey, CTS, gat or plot numbers

PLOT NO 05 GUT NO 105 PART

Boundaries

North
Plot No 02 And Open Space
South
18 Meter Wide Road
East
Approved Layout At Gut No 105
West
Plot No 06

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectR B Associates—
Chartered accountantSudarshan Karwa And Co—
EngineerB V Raut—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology