Ganeshkunj Apartment

Completed

Hirapur, Aurangabad 431207 |Promoter: Gurulaxmi Builders

Residential / Group HousingRERAP51500011695
31 Aug 2017Registered with MahaRERA
27 Feb 2019Promised completion
30 Sep 2022Revised completionPushed back 3 years and 7 months
1Building
24Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
1 BHK, 1 RK24 units in all
Land area for this project
724 sq m (7,795 sq ft)
Permissible built-up area
869 sq m (9,354 sq ft)
Sanctioned built-up area
724 sq m (7,795 sq ft)
Address
64-66, Jalna Road, Near Sai Baba MandirPIN 431207
Designated bank account
Saraswat Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.05517, 72.82995
Ganeshkunj Apartment is at latitude 19.05517, longitude 72.82995.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years and 7 months

The latest completion date on record passed 4 years and 1 month ago.

Registered
31 Aug 2017
Promised
27 Feb 2019
Revised
30 Sep 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150001169531 Aug 201727 Feb 201930 Sep 2022Gurulaxmi BuildersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Ganeshkunj624

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

24 units registered

1 BHK · 22 units1 RK · 2 units
TypeCarpet areaUnits
1 BHK33.81 sq m · 364 sq ft14
1 BHK35.4 sq m · 381 sq ft8
1 RK23.5 sq m · 253 sq ft2

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Ganeshkunj

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

22 documents held by Deedo, 26 filings listed on MahaRERA's project page

Others

Registration certificate

Extension certificate

Document library

  • Copy of the legal title reportSEARCH REPORT.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)layout.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterADVOCATE PROFARMA_ATS.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CETIFICATE.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certiuficate.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)Parking floor.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)First Floor.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)Stilt Fourt Floor plan.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)Elavation.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesLetter of emb.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eNG.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BScan B.pdf · uploaded 31 Jul 2017View
  • Certificates of CA (Form 5)CA Certificate Form 5.pdf · uploaded 2 Apr 2019View
  • Architect’s Certificate on Completion of Project (Form 4)Completion certificate.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form No 5.pdf · uploaded 11 Apr 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form No 5.pdf · uploaded 11 Apr 2023View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Society Formation Certificate.pdf · uploaded 17 Jan 2024View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate.pdf · uploaded 17 Jan 2024View

Promoter documents

  • Legal Title reportSEARCH REPORT.pdf · uploaded 31 Jul 2017View
  • Declaration Form BScan B.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout Approvallayout.pdfView
  • Building Plan ApprovalStilt Fourt Floor plan.pdfView
  • Building Plan ApprovalElavation.pdfView
  • Building Plan ApprovalParking floor.pdfView
  • Building Plan ApprovalFirst Floor.pdfView

Proforma allotment letter

  • Proforma allotment letterADVOCATE PROFARMA_ATS.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hirapur, Aurangabad taluka

Survey, CTS, gat or plot numbers

6466

As published on MahaRERA's project page

64-66

Boundaries

North
12 Meters Road
South
Plot No 67
East
Ammenity Space
West
6 Meters Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr.Pranay Shrikant Chandratreya—
EngineerMr. Vivek Apte—

Source: MahaRERA project page. Contact details are not shown.