Tirupati Tower

Completed

Aurangabad (M Corp.), Aurangabad 431007 |Promoter: Pradeep Suryakant Bapte

18 Aug 2017Registered with MahaRERA
31 Mar 2019Promised completion
1Building
18Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
1BHK, Shop18 units in all
Land area for this project
306 sq m (3,298 sq ft)
Permissible built-up area
499 sq m (5,371 sq ft)
Sanctioned built-up area
297 sq m (3,195 sq ft)
Address
Plot No A9 Gut No 32/2PIN 431007
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.05497, 79.07686
Tirupati Tower is at latitude 21.05497, longitude 79.07686.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2019

The latest completion date on record passed 7 years and 7 months ago.

Registered
18 Aug 2017
Promised
31 Mar 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000827318 Aug 201731 Mar 2019—Pradeep Suryakant BapteProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Tirupati Tower618

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

18 units registered

1BHK · 14 unitsShop · 4 units
TypeCarpet areaUnits
1BHK28.15 sq m · 303 sq ft4
1BHK34.2 sq m · 368 sq ft5
1BHK35.2 sq m · 379 sq ft5
Shop7.7 sq m · 83 sq ft2
Shop12.1 sq m · 130 sq ft2

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Tirupati Tower

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises20%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyTO BE SUPPLIED BY AMC ALSO ONE BOREWELL50%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingTO BE COMPLETED0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingTO BE COMPLETED50%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

14 documents held by Deedo, 16 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Form 1

Form 2

Registration certificate

Form 5

Show all 30 documentsShow fewer documents

Form 4

Other (2)

Layout plan

Building plan

Allotment letter

Document library

  • Copy of the legal title reportSEARCH REPORT.pdf · uploaded 30 Jul 2017View
  • Details of encumbrancesENC.pdf · uploaded 30 Jul 2017View
  • Copy of Layout Approval (in case of layout)PLAN 1.pdf · uploaded 30 Jul 2017View
  • Declaration in FORM BFORM B.pdf · uploaded 30 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCOMMEMCEMENT CERT.pdf · uploaded 30 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)PLAN.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment letterAGREEMENT.pdf · uploaded 30 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 30 Jul 2017View
  • Certificates of CA (Form 5)form 5 annual retport.pdf · uploaded 15 Oct 2018View
  • Architect’s Certificate on Completion of Project (Form 4)COMPLETION_SELF_DEC.pdf · uploaded 13 Feb 2021View

Promoter documents

  • Legal Title reportSEARCH REPORT.pdf · uploaded 30 Jul 2017View
  • Declaration Form BFORM B.pdf · uploaded 30 Jul 2017View

Technical documents

  • Layout ApprovalPLAN 1.pdfView
  • Building Plan ApprovalPLAN.pdfView

Proforma allotment letter

  • Proforma allotment letterAGREEMENT.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

PLOT NO A9 GUT NO 32/2

As published on MahaRERA's project page

PLOT NO A9 GUT NO 32/2

Boundaries

North
Road
South
Plot No A10
East
Road
West
8a

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDhananjay Doifode—
EngineerShafique Khan—
OtherAmol Mundhe—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology