Aurangabad (M Corp.), Aurangabad 431105 |Promoter: Uttam Bhaurao Patil, Ashish Uttamrao Patil And Priti Sudhir Maknikar

Residential / Group HousingRERAP51500045627
26 May 2022Registered with MahaRERA
31 Dec 2026Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Land area for this project
421 sq m (4,532 sq ft)
Permissible built-up area
1,444 sq m (15,540 sq ft)
Sanctioned built-up area
1,344 sq m (14,464 sq ft)
Planning authority
Aurangabad Mahanagarpalika
Address
Plot No 12 and 13 Gut No 47P Itkheda, Paithan Road, ItkhedaPIN 431105
Designated bank account
Bank Of Maharashtra
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.84326, 75.29897
Surekha Residency is at latitude 19.84326, longitude 75.29897.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2026

Registered
26 May 2022
Promised
31 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150004562726 May 202231 Dec 2026—Uttam Bhaurao Patil, Ashish Uttamrao Patil And Priti Sudhir MaknikarProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Surekha Residency8—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Surekha Residency

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCompleted100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Completed100%
  • Storm Water DrainsCompleted100%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCompleted100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsAs per norms Completed100%
  • Electrical meter room, sub-station, receiving stationCompleted100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

72 documents held by Deedo, 121 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Proforma of Allotment letterAgreement To Sale Uttam Patil_0001.pdf · uploaded 17 May 2022View
  • CERSAI detailsCERSAI_Search_Report_200237303325_For_Asset_Based_Search_13_05_2022_17_38_00_329.pdf · uploaded 17 May 2022View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate_0001_1.pdf · uploaded 17 May 2022View
  • Details of encumbrancesNon encumbrance Declaration Mr Uttam Patil_0001.pdf · uploaded 17 May 2022View
  • Declaration about Commencement CertificateDeclaration About Commencemnt Certificate Mr Utttam Patil_0001.pdf · uploaded 17 May 2022View
  • Declaration in FORM BForm ''B'' DeclarationMr Uttam Patil_0001.pdf · uploaded 17 May 2022View
  • Copy of the legal title reportLegal Titile Report Mr Uttam Patil_0001.pdf · uploaded 17 May 2022View
  • Proforma of Allotment letterAllotment letter_0001.pdf · uploaded 17 May 2022View
  • Copy of Layout Approval (in case of layout)scan0169_11zon.pdf · uploaded 21 May 2022View
  • Building Plan Approval / NA Order for plotted developmentscan0169_11zon.pdf · uploaded 21 May 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate_0001.pdf · uploaded 22 Jul 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2_0001.pdf · uploaded 22 Jul 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Certificate_0001.pdf · uploaded 22 Jul 2022View
  • Disclosure of sold/ booked inventory123_0001.pdf · uploaded 22 Jul 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 19 Oct 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 19 Oct 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Annexure C_0001.pdf · uploaded 19 Oct 2022View
  • Disclosure of sold/ booked inventoryUttam bhaurao patil builder_0001.pdf · uploaded 19 Oct 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 (1).pdf · uploaded 13 Jan 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 13 Jan 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)surekha residency form - 2A_0001.pdf · uploaded 13 Jan 2023View
  • Disclosure of sold/ booked inventorySurekha residency -_0001.pdf · uploaded 13 Jan 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)4 (2 files merged).pdf · uploaded 27 Apr 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)1 (3 files merged).pdf · uploaded 27 Apr 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2 Engineer.pdf · uploaded 27 Apr 2023View
  • Disclosure of sold/ booked inventoryDisclosure Of Sold Inventory.pdf · uploaded 27 Apr 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate Surekha Residency_0001.pdf · uploaded 26 Jul 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Surekha Residency_0001.pdf · uploaded 26 Jul 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer Certificate Surekha Residency Ann C_0001.pdf · uploaded 26 Jul 2023View
  • Disclosure of sold/ booked inventoryPromoters Letterhead Surekha Residency_0001.pdf · uploaded 26 Jul 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form no 1 Dt 04102023_0001.pdf · uploaded 2 Nov 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form no 2 Dt 04102023_0001.pdf · uploaded 2 Nov 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form no 2A Dt 04102023_0001.pdf · uploaded 2 Nov 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form no 5 Dt04102023_0001.pdf · uploaded 2 Nov 2023View
  • Disclosure of sold/ booked inventoryDisclosure of sold -booked inventory_0001.pdf · uploaded 2 Nov 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Document_1707113941304.pdf · uploaded 5 Feb 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form no2 Surekha Residency_0001.pdf · uploaded 5 Feb 2024View
  • Disclosure of sold/ booked inventoryDiscloser of Surekha Residency_0001.pdf · uploaded 5 Feb 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form no2A Uttam Patil,Ashish Patil Sudhir M_0001.pdf · uploaded 5 Feb 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Surekha Res dt04-04-2024_0001.pdf · uploaded 27 May 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Surekha Res dt04-04-2024_0001.pdf · uploaded 27 May 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Surekha Res dt04-04-2024_0001.pdf · uploaded 27 May 2024View
  • Disclosure of sold/ booked inventoryDesclosure of Sold books inve_0001.pdf · uploaded 27 May 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form no 1 of Uttam Bhaurao Patil_0001.pdf · uploaded 20 Jul 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form no 2A of Uttam Bhaurao Patil_0001.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Prasad Aphale.pdf · uploaded 27 Jul 2024View
  • Disclosure of sold/ booked inventorySold-Book Inventory_0001.pdf · uploaded 29 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form -1.pdf · uploaded 19 Oct 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A.pdf · uploaded 19 Oct 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Annexure F.pdf · uploaded 19 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 uttam patil_0001.pdf · uploaded 8 Nov 2024View
  • Disclosure of sold/ booked inventoryDisclosure_0001.pdf · uploaded 8 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)New Doc 01-22-2025.pdf · uploaded 22 Jan 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Rera Engineer (3).pdf · uploaded 22 Jan 2025View
  • Disclosure of sold/ booked inventoryLeter Head Of Uttam Patil dt-04-01-2025_0001.pdf · uploaded 22 Jan 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A To Uttam B Patil Dt-04-01-2025_0001.pdf · uploaded 22 Jan 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)fORM 1_0001.pdf · uploaded 26 Apr 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A_0001.pdf · uploaded 26 Apr 2025View
  • Disclosure of sold/ booked inventoryDisclosure_0001.pdf · uploaded 26 Apr 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Architect Certificate Dt-04-07-2025_0001.pdf · uploaded 20 Aug 2025View
  • Form 2Form-2 Engineers.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Dt-10-07-2025_0001.pdf · uploaded 20 Aug 2025View
  • OthersForm-2A Engineers CertificateFor Quality Assurance_0001.pdf · uploaded 20 Aug 2025View
  • Occupational Certificateoc.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDisc.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 1Form 1_0001.pdf · uploaded 20 Aug 2025View
  • Form 2Form 2.pdf · uploaded 20 Aug 2025View
  • Disclosure of Sold and Booked InventoryDISC.pdf · uploaded 20 Aug 2025View
  • OthersForm 2A.pdf · uploaded 20 Aug 2025View
  • Form 5 (FY 2024-2025)rera report.pdf · uploaded 29 Sep 2025View
  • Occupational CertificateSUREKHA RESIDENCY OC Plan.pdf · uploaded 14 Nov 2025View
  • Occupational CertificateSurekha Residency_0001.pdf · uploaded 14 Nov 2025View

Promoter documents

  • Declaration Form BForm ''B'' DeclarationMr Uttam Patil_0001.pdf · uploaded 17 May 2022View
  • Legal Title reportLegal Titile Report Mr Uttam Patil_0001.pdf · uploaded 17 May 2022View

Technical documents

  • Layout Approvalscan0169_11zon.pdfView
  • Building Plan Approvalscan0169_11zon.pdfView
  • Building Plan ApprovalSUREKHA RESIDENCY OC Plan.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment letter_0001.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

13 Gut No 47P ItkhedaPlot No 12

As published on MahaRERA's project page

Plot No 12 and 13 Gut No 47P Itkheda

Boundaries

North
Plot No 14
South
9 Mtr Wide Road
East
9 Mtr Road
West
Land of Revati Co op hsg society

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNishant Tawde—
Chartered accountantD B Dighe & Co—
EngineerPrasad Amphale—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology