Lapsed

Aurangabad (M Corp.), Aurangabad 431005 |Promoter: Shree Sai

Residential / Group HousingRERAP51500005773
14 Aug 2017Registered with MahaRERA
30 Dec 2022Promised completion
1Building
9Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
1
Unit types
Residential9 units in all
Land area for this project
423 sq m (4,553 sq ft)
Permissible built-up area
577 sq m (6,207 sq ft)
Sanctioned built-up area
577 sq m (6,207 sq ft)
Address
Plot No 17 Gut No 47 Part ItkhedaPIN 431005
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.15934, 72.84269
Shree Sai is at latitude 19.15934, longitude 72.84269.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2022

The latest completion date on record passed 3 years and 10 months ago.

Registered
14 Aug 2017
Promised
30 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150000577314 Aug 201730 Dec 2022—Shree SaiProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shree Sai59

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

9 units registered

Residential · 9 units
TypeCarpet areaUnits
Residential539.91 sq m · 5,812 sq ft9

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00009

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shree Sai

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supply100100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)100100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage Water100100%
  • Solid Waste Management And Disposal100100%
  • Water conservation /Rain water harvesting100100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving station100100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parking100100%
  • OPEN PARKING AND LOBBIES AND LIFT100100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

27 documents held by Deedo, 30 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title reportSEARCH_REPORT_SHREE_SAI07312017151014.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesSEARCH_REPORT_SHREE_SAI07312017151014.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)NA_ORDER_SHREE_SAI07312017150638.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterSAI KUMBH RECPIT07312017194014.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BFORM_B_SHREE_SAI COMPRESS.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE(SHREE SAI)07312017141147.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)BUILDING PERMISSION.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS_CERTIFICATE_SHREE_SAI_07312017140630.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterSALE_DEED.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE SHREE SAI07312017150512.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Shrisai.pdf · uploaded 28 Mar 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Engineers Certificate Shrisai 18.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineers Certificate 18-19 Shri Sai-.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)engineer Certification Shrisai 19-20.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineers certificate Shrisai 20-21.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineers Certificate Shrisai 21-22.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)EQA Certificate 18.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)EQA Certificate SS 19.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)EQA Certificate SS 20_compressed.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)EQA Certificate SS 21_compressed.pdf · uploaded 28 Mar 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)EQA Certificate SS 22_compressed.pdf · uploaded 28 Mar 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)CA SS 18-19_compressed.pdf · uploaded 28 Mar 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)CA SS 19-20_compressed.pdf · uploaded 28 Mar 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA SS 20-21_compressed.pdf · uploaded 28 Mar 2023View
  • Disclosure of sold/ booked inventoryShree Sai booked inventory.pdf · uploaded 20 Apr 2023View

Promoter documents

  • Legal Title reportSEARCH_REPORT_SHREE_SAI07312017151014.pdf · uploaded 31 Jul 2017View
  • Declaration Form BFORM_B_SHREE_SAI COMPRESS.pdf · uploaded 31 Jul 2017View

Technical documents

  • Building Plan ApprovalBUILDING PERMISSION.pdfView
  • Layout ApprovalNA_ORDER_SHREE_SAI07312017150638.pdfView

Proforma allotment letter

  • Proforma allotment letterSALE_DEED.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

PLOT NO 17 GUT NO 47 PART ITKHEDA

As published on MahaRERA's project page

PLOT NO 17 GUT NO 47 PART ITKHEDA

Boundaries

North
Road
South
Plot No 16 A And B
East
Plot No 19
West
9 Mtrs Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKedar Pande—