Completion due Dec 2026

Aurangabad (M Corp.), Aurangabad 431001 |Promoter: Shinde Properties Private Limited

17 Mar 2022Registered with MahaRERA
31 Mar 2025Promised completion
31 Dec 2026Revised completionPushed back 1 year and 9 months
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

MahaRERA's search listing gives this project's name, promoter and location only.

MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 9 months

Registered
17 Mar 2022
Promised
31 Mar 2025
Revised
31 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150003400717 Mar 202231 Mar 202531 Dec 2026Shinde Properties Private LimitedProject page

Documents

2 documents held by Deedo

Registration certificate

Extension certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.)

Survey, CTS, gat or plot numbers

CTS NO 4642 NAGESHWARWADI AURANGABAD

Source: registration certificates, as stated there.