Sai Pratik Nagari

Certificate Signed

Aurangabad (M Corp.), Aurangabad 431005 |Promoter: Pratik Dream Home

Residential / Group HousingRERAP51500020695
3 May 2019Registered with MahaRERA
31 May 2027Promised completion
30 Sep 2027Revised completionPushed back 4 months
6Buildings
80Units registered72 booked (90%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
6
Unit types
3BHK ROW HOUSE, 2BHK ROW HOUSE, 1 BHK FLAT, 2 BHK ROW HOUSE80 units in all
Address
Gut No 128, Village Deolai, Aurangabad, Khadi Road, DeolaiPIN 431005
Designated bank account
43
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.87617, 75.34331
Sai Pratik Nagari is at latitude 19.87617, longitude 75.34331.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
3 May 2019
Promised
31 May 2027
Revised
30 Sep 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000206953 May 201931 May 202730 Sep 2027Pratik Dream HomeProject page

6 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building A28
Building B320
Building C416
Building D320
Building E28
Building F48

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

72 of 80 units booked (90%), as the promoter reported to MahaRERA

3BHK ROW HOUSE · 16 units2BHK ROW HOUSE · 28 units1 BHK FLAT · 16 units2 BHK ROW HOUSE · 20 units
BuildingTypeCarpet areaUnitsBooked
Building A3BHK ROW HOUSE76.5 sq m · 823 sq ft88
Building B2BHK ROW HOUSE55.5 sq m · 597 sq ft2016
Building C1 BHK FLAT29.3 sq m · 315 sq ft1612
Building D2 BHK ROW HOUSE55.5 sq m · 597 sq ft2020
Building E3BHK ROW HOUSE76.5 sq m · 823 sq ft88
Building F2BHK ROW HOUSE55.1 sq m · 593 sq ft88

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 123 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Declaration Form BDeclaration Form B.pdf · uploaded 27 Apr 2019Source
  • Legal Title reportLegal Search Report.pdf · uploaded 27 Apr 2019Source
  • Declaration Form BBond for rera.pdf · uploaded 12 Aug 2023Source
  • Declaration Form BFORM B Developer New Revised.pdf · uploaded 30 Mar 2024Source

Migrated

  • 1 PAN CardPAN Pratik Dream Home.pdf · uploaded 27 Apr 2019Source
  • 1 Copy of the legal title reportLegal Search Report.pdf · uploaded 27 Apr 2019Source
  • 1 Details of encumbrancesDeclaration of Encumbrances.pdf · uploaded 27 Apr 2019Source
Show all 124 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 27 Apr 2019Source
  • 1 Building Plan Approval (IOD)Approved Plan Building ABC.pdf · uploaded 27 Apr 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 27 Apr 2019Source
  • 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 27 Apr 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 27 Apr 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 27 Apr 2019Source
  • 1 Certificates of CA (Form 3)Rera Certificate Pratik Dream Home Sai Pratik Nagari_compressed (1).pdf · uploaded 27 Apr 2019Source
  • 1 Proforma of Allotment letterProforma of ATOS And Allotment Letter.pdf · uploaded 27 Apr 2019Source
  • 1 OtherApproved Plan Building EFC.pdf · uploaded 27 Apr 2019Source
  • 1 Declaration about Commencement CertificateDeclaration About Commencement Cert.pdf · uploaded 11 Apr 2022Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate Pratik Dream.pdf · uploaded 11 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineer Quality Certificate 2(a).pdf · uploaded 11 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer Quality Certificate 2(a).pdf · uploaded 11 Apr 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200234914204_For_Asset_Based_Search_09_04_2022_13_08_02_030.pdf · uploaded 11 Apr 2022Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 11 Apr 2022Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Updated.pdf · uploaded 12 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Mar-20 Statement.pdf · uploaded 12 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Mar-21 Statement.pdf · uploaded 12 Apr 2022Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect's Certificate.pdf · uploaded 18 Jul 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 18 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineers Certificate on Quality Assurance (Form 2A FY 2021 - 22).pdf · uploaded 18 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineers Certificate on Quality Assurance (Form 2A FY 2021 - 22).pdf · uploaded 18 Jul 2023Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 18 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form No 5.pdf · uploaded 18 Jul 2023Source
  • 2 Declaration in FORM BBond for rera.pdf · uploaded 12 Aug 2023Source
  • 2 Certificates of CA (Form 3)Signed Form 3.pdf · uploaded 17 Aug 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 23 Aug 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 23 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A 19-20.pdf · uploaded 23 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A 20-21.pdf · uploaded 23 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A 21-22.pdf · uploaded 23 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A 22-23.pdf · uploaded 23 Aug 2023Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 23 Aug 2023Source
  • 2 a Details of encumbrances concerned to Finance1 Merged Encumbarences.pdf · uploaded 30 Mar 2024Source
  • 1 b Details of encumbrances concerned to Legal1 Merged Encumbarences.pdf · uploaded 30 Mar 2024Source
  • 3 Declaration in FORM BFORM B Developer New Revised.pdf · uploaded 30 Mar 2024Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Architect.pdf · uploaded 30 Mar 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert.pdf · uploaded 30 Mar 2024Source
  • 4 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 30 Mar 2024Source
  • 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 30 Mar 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizations5 Disclosure of interest.pdf · uploaded 30 Mar 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same9 Seprate Bank Account Declaration.pdf · uploaded 30 Mar 2024Source
  • 1 Deviation Report with respect to Allotment letter3 Deviation Report with respect to Allotment letter ok.pdf · uploaded 30 Mar 2024Source
  • 1 Deviation Report with respect to model copy of Agreement4 Deviation Report with respect to model copy of Agreement ok.pdf · uploaded 30 Mar 2024Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 10 Jun 2024Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2022 Q1.pdf · uploaded 9 Jul 2024Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2022 Q2.pdf · uploaded 9 Jul 2024Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2022 Q3.pdf · uploaded 9 Jul 2024Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2023 Q1.pdf · uploaded 9 Jul 2024Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2023 Q2.pdf · uploaded 9 Jul 2024Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2023 Q3.pdf · uploaded 9 Jul 2024Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2023 Q4.pdf · uploaded 9 Jul 2024Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 2024 Q4.pdf · uploaded 9 Jul 2024Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2020 Q4_.pdf · uploaded 10 Jul 2024Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2021 Q4_.pdf · uploaded 10 Jul 2024Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2022 Q4_.pdf · uploaded 10 Jul 2024Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2022 Q1_.pdf · uploaded 10 Jul 2024Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2022 Q2_.pdf · uploaded 10 Jul 2024Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2022 Q3_.pdf · uploaded 10 Jul 2024Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2023 Q4_.pdf · uploaded 10 Jul 2024Source
  • 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2023 Q1_.pdf · uploaded 10 Jul 2024Source
  • 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)From 2 2023 Q2_.pdf · uploaded 10 Jul 2024Source
  • 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2023 Q3_.pdf · uploaded 10 Jul 2024Source
  • 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 2024 Q4_.pdf · uploaded 10 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2024 Q4_.pdf · uploaded 10 Jul 2024Source
  • 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 19-20.pdf · uploaded 22 Jul 2024Source
  • 19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 20-21.pdf · uploaded 22 Jul 2024Source
  • 20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 21-22.pdf · uploaded 22 Jul 2024Source
  • 21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 22-23 Q1.pdf · uploaded 22 Jul 2024Source
  • 22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 22-23 Q2.pdf · uploaded 22 Jul 2024Source
  • 23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 22-23 Q3.pdf · uploaded 22 Jul 2024Source
  • 24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 22-23 Q4.pdf · uploaded 22 Jul 2024Source
  • 25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 23-24 Q1.pdf · uploaded 22 Jul 2024Source
  • 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 23-24 Q2.pdf · uploaded 22 Jul 2024Source
  • 27 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 23-24 Q3.pdf · uploaded 22 Jul 2024Source
  • 28 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Cert 23-24 Q4.pdf · uploaded 22 Jul 2024Source
  • 5 Disclosure of sold/ booked inventorySold Unsold 2022-23 Q1.pdf · uploaded 24 Jul 2024Source
  • 6 Disclosure of sold/ booked inventorySold Unsold 2022-23 Q2.pdf · uploaded 24 Jul 2024Source
  • 7 Disclosure of sold/ booked inventorySold Unsold 2022-23 Q3.pdf · uploaded 24 Jul 2024Source
  • 8 Disclosure of sold/ booked inventorySold Unsold 2022-23 Q4.pdf · uploaded 24 Jul 2024Source
  • 9 Disclosure of sold/ booked inventorySold Unsold 2023-24 Q1.pdf · uploaded 24 Jul 2024Source
  • 10 Disclosure of sold/ booked inventorySold Unsold 2023-24 Q2.pdf · uploaded 24 Jul 2024Source
  • 11 Disclosure of sold/ booked inventorySold Unsold 2023-24 Q3.pdf · uploaded 24 Jul 2024Source
  • 12 Disclosure of sold/ booked inventorySold Unsold 2023-24 Q4.pdf · uploaded 24 Jul 2024Source
  • 4 Certificates of CA (Form 3)Form 3 2022-23 Q1.pdf · uploaded 26 Jul 2024Source
  • 5 Certificates of CA (Form 3)Form 3 2022-23 Q2.pdf · uploaded 26 Jul 2024Source
  • 6 Certificates of CA (Form 3)Form 3 2022-23 Q3.pdf · uploaded 26 Jul 2024Source
  • 7 Certificates of CA (Form 3)Form 3 2022-23 Q4.pdf · uploaded 26 Jul 2024Source
  • 8 Certificates of CA (Form 3)Form 3 2023-24 Q2.pdf · uploaded 26 Jul 2024Source
  • 9 Certificates of CA (Form 3)Form 3 2023-24 Q4.pdf · uploaded 26 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-23.pdf · uploaded 26 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 2023-24.pdf · uploaded 26 Jul 2024Source
  • 10 Certificates of CA (Form 3)Form 3 22-23 Q1.pdf · uploaded 29 Jul 2024Source
  • 11 Certificates of CA (Form 3)Form 3 22-23 Q2.pdf · uploaded 29 Jul 2024Source
  • 12 Certificates of CA (Form 3)Form 3 22-23 Q3.pdf · uploaded 29 Jul 2024Source
  • 13 Certificates of CA (Form 3)Form 3 22-23 Q4.pdf · uploaded 29 Jul 2024Source
  • 14 Certificates of CA (Form 3)Form 3 23-24 Q2.pdf · uploaded 29 Jul 2024Source
  • Withdrawal Update Form 1Form 1 2025-26 Q1.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1Form 1 2025-26 Q2.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1Form 1 2025-26 Q2.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1Form 1 2025-26 Q4.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1Form 1 2025-26 Q4.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2Form 2 2025-26 Q1.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2Form 2 2025-26 Q1.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2Form 2 2025-26 Q1.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2Form 2 2025-26 Q4.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2Form 2 2025-26 Q4.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3Form 3 2025-26 Q1.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3Form 3 2025-26 Q2.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3Form 3 2025-26 Q3.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3Form 3 2025-26 Q4.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3Form 3 2025-26 Q4.pdf · uploaded 30 May 2026Source

Technical

  • DocumentApproved Plan Building ABC.pdf · uploaded 27 Apr 2019Source
  • DocumentLayout Plan.pdf · uploaded 27 Apr 2019Source

Technical (Architect)

  • DocumentForm 1 2025-26 Q4.pdf · uploaded 30 May 2026Source

Technical (Engineer)

  • DocumentForm 2 2025-26 Q4.pdf · uploaded 30 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

GUT NO 128

Boundaries

North
Land Of Gut No 127
South
Remaining Land Gut No 128
East
Remaining Land Gut No 128
West
Remaining Land Gut No 128

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Dhananjay B Doifode—
ArchitectAshok Balande—
Chartered accountantCa Girish Padmakar Awalgaonkar—
Chartered accountantCa Vaibhav Vijay Dande—
EngineerEr Abhay S Patil—

Source: MahaRERA project page. Contact details are not shown.