Skip to content
Deedo home
Menu

Sai Krupa Apartment

Lapsed

Aurangabad (M Corp.), Aurangabad 431005 |Promoter: Sai Ambika Developers

Residential / Group HousingRERAP51500020882
15 May 2019Registered with MahaRERA
31 Jul 2019Promised completion
1Building
16Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
1
Unit types
1BHK16 units in all
Land area for this project
357 sq m (3,843 sq ft)
Permissible built-up area
500 sq m (5,380 sq ft)
Sanctioned built-up area
500 sq m (5,380 sq ft)
Address
Plot No 02, Gut No 20 Part, Datta Nagar KanchanwadiPIN 431005
Designated bank account
Nkgsb Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Sai Krupa Apartment is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Jul 2019

The latest completion date on record passed 7 years and 3 months ago.

Registered
15 May 2019
Promised
31 Jul 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150002088215 May 201931 Jul 2019—Sai Ambika DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Sai Krupa Apartment616

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

16 units registered

1BHK · 16 units
TypeCarpet areaUnits
1BHK28.33 sq m · 305 sq ft16

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Sai Krupa Apartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBorewell100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Drainage line100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingUp to the well100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationMeter100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

10 documents held by Deedo, 14 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Commencement Certificates / NA Order for plotted developmentBuilding Permission Sai Krupa.pdf · uploaded 5 May 2019View
  • Copy of the legal title reportSearch.pdf · uploaded 5 May 2019View
  • Details of encumbrancesSearch.pdf · uploaded 5 May 2019View
  • Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 5 May 2019View
  • Building Plan Approval (IOD)Plan.pdf · uploaded 5 May 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Eng Cer.pdf · uploaded 5 May 2019View
  • Proforma of Allotment letterATS 1.pdf · uploaded 5 May 2019View
  • Proforma of Allotment letterATS 2.pdf · uploaded 5 May 2019View
  • Declaration in FORM BFormB.pdf · uploaded 5 May 2019View

Promoter documents

  • Legal Title reportSearch.pdf · uploaded 5 May 2019View
  • Declaration Form BFormB.pdf · uploaded 5 May 2019View

Technical documents

  • Layout ApprovalPlan.pdfView
  • Building Plan ApprovalPlan.pdfView

Proforma allotment letter

  • Proforma allotment letterATS 2.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

02Plot No 02

As published on MahaRERA's project page

Plot No 02

Boundaries

North
Plot No 03
South
Plot No 01
East
Plot No 25 and 26
West
9 Meter Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDhananjay B Doifode—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology