Pratik Angan

Active

Aurangabad (M Corp.), Aurangabad 431002 |Promoter: Pratik Abhiruchi

27 Jun 2023Registered with MahaRERA
31 Dec 2028Promised completion
4Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Active
Buildings
4
Land area for this project
3,300 sq m (35,521 sq ft)
Permissible built-up area
5,051 sq m (54,368 sq ft)
Sanctioned built-up area
5,051 sq m (54,368 sq ft)
Planning authority
chatrapati sambhajinagar municipal corporation
Address
Gut No. 08/Part, Nakshatrawadi, Gut No, 08/Part, Nakshtrawadi, Aurangabad-431002., Nakshatrawadi, AurangabadPIN 431002
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.81221, 75.28792
Pratik Angan is at latitude 19.81221, longitude 75.28792.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2028

Registered
27 Jun 2023
Promised
31 Dec 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150005177327 Jun 202331 Dec 2028—Pratik AbhiruchiProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A Type Row Houses2—
B Type Row Houses1—
C Type Row Houses1—
D and E Type Building7—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
A Type Row HousesClosed/Covered00001
A Type Row HousesOpen Space00004
B Type Row HousesClosed/Covered00000
B Type Row HousesOpen Space00000
C Type Row HousesClosed/Covered00000
C Type Row HousesOpen Space00000
D and E Type BuildingClosed/Covered00000
D and E Type BuildingOpen Space000080

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

A Type Row Houses

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

B Type Row Houses

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

C Type Row Houses

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

D and E Type Building

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure70%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.3%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsAS PER APPROVED PLAN100%
  • Water SupplyAS PER APPROVED PLAN0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER APPROVED PLAN80%
  • Storm Water DrainsAS PER APPROVED PLAN0%
  • Landscaping & Tree PlantingAS PER APPROVED PLAN5%
  • Street LightingAS PER APPROVED PLAN50%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER APPROVED PLAN0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsAS PER APPROVED PLAN0%
  • Electrical meter room, sub-station, receiving stationAS PER APPROVED PLAN100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

52 documents held by Deedo, 59 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Commencement Certificates / NA Order for plotted developmentRevised Commencment.pdf · uploaded 20 Apr 2023View
  • Copy of the legal title reportlegal title report 12_11zon.pdf · uploaded 24 Apr 2023View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samesaperate bank account declaration 9.pdf · uploaded 24 Apr 2023View
  • Deviation Report with respect to Allotment letterdeviation report with respect to allotment letter 5.pdf · uploaded 24 Apr 2023View
  • Deviation Report with respect to model copy of AgreementDeviation report with respect to the model copy of agreement 4.pdf · uploaded 24 Apr 2023View
  • a Details of encumbrances concerned to Financecertificate and encumbrances legal merged (1).pdf · uploaded 24 Apr 2023View
  • b Details of encumbrances concerned to Legalcertificate and encumbrances legal merged (1).pdf · uploaded 24 Apr 2023View
  • Proforma of Allotment letterAllotment Letter_11zon.pdf · uploaded 25 Apr 2023View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclouser.pdf · uploaded 25 Apr 2023View
  • CERSAI detailsCERSAI_Search_Report_200266850168_For_Asset_Based_Search_24_04_2023_16_18_14_434.pdf · uploaded 25 Apr 2023View
  • Declaration in FORM BForm B Developer.pdf · uploaded 26 Apr 2023View
  • Proforma of Agreement for saleFinal ATS.pdf · uploaded 26 Apr 2023View
  • Disclosure of sold/ booked inventorySold unsold 1.pdf · uploaded 30 May 2023View
  • Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 5 Jun 2023View
  • Building Plan Approval / NA Order for plotted developmentA Building.pdf · uploaded 5 Jun 2023View
  • Building Plan Approval / NA Order for plotted developmentB Building.pdf · uploaded 5 Jun 2023View
  • Building Plan Approval / NA Order for plotted developmentC Building.pdf · uploaded 5 Jun 2023View
  • Building Plan Approval / NA Order for plotted developmentD and E Building.pdf · uploaded 5 Jun 2023View
  • Building Plan Approval / NA Order for plotted developmentD and E.pdf · uploaded 5 Jun 2023View
  • Building Plan Approval / NA Order for plotted developmentD and E 2.pdf · uploaded 5 Jun 2023View
  • Declaration about Commencement CertificateDeclaration abaout commencement certificate new.pdf · uploaded 13 Jun 2023View
  • Disclosure of sold/ booked inventoryDisclosue of booked inventory 2023 Q1.pdf · uploaded 10 Jul 2024View
  • Disclosure of sold/ booked inventoryDisclosue of booked inventory 2023 Q2.pdf · uploaded 10 Jul 2024View
  • Disclosure of sold/ booked inventoryDisclosue of booked inventory 2023 Q3.pdf · uploaded 10 Jul 2024View
  • Disclosure of sold/ booked inventoryDisclosue of booked inventory 2024 Q4.pdf · uploaded 10 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2023-24 Q1.pdf · uploaded 20 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2023-24 Q2.pdf · uploaded 20 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2023-24 Q3.pdf · uploaded 20 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2023-24 Q4.pdf · uploaded 20 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2024-25 Q1.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 2023-24 Q1.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 2023-24 Q2.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 2023-24 Q3.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 2023-24 Q4.pdf · uploaded 20 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 2024-25 Q1.pdf · uploaded 20 Jul 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 23-24 Signed.pdf · uploaded 28 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2024-25 Q2.pdf · uploaded 19 Apr 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2024-25 Q3.pdf · uploaded 19 Apr 2025View
  • Disclosure of sold/ booked inventorysold unsold Q1.pdf · uploaded 26 Apr 2025View
  • Disclosure of sold/ booked inventorysold unsold Q2.pdf · uploaded 26 Apr 2025View
  • Disclosure of sold/ booked inventorysold unsold Q3.pdf · uploaded 26 Apr 2025View
  • Withdrawal Update Form 1Form 1 2025-26 Q1.pdf · uploaded 12 Mar 2026View
  • Withdrawal Update Form 2Form 2 2025-26 Q1.pdf · uploaded 12 Mar 2026View
  • Withdrawal Update Form 1Form 1 2025-26 Q2.pdf · uploaded 12 Mar 2026View
  • Withdrawal Update Form 2Form 2 2025-26 Q2.pdf · uploaded 12 Mar 2026View
  • Withdrawal Update Form 1Form 1 2025-26 Q3.pdf · uploaded 12 Mar 2026View
  • Withdrawal Update Form 2Form 2 2025-26 Q3.pdf · uploaded 12 Mar 2026View
  • Withdrawal Update Form 1Form 1 2025-26 Q4..pdf · uploaded 27 Jun 2026View
  • Withdrawal Update Form 2Form 2 2025-26 Q3.pdf · uploaded 27 Jun 2026View

Promoter documents

  • Legal Title reportlegal title report 12_11zon.pdf · uploaded 24 Apr 2023View
  • Declaration Form BForm B Developer.pdf · uploaded 26 Apr 2023View

Technical documents

  • Layout ApprovalLayout Plan.pdfView
  • Building Plan ApprovalA Building.pdfView
  • Building Plan ApprovalB Building.pdfView
  • Building Plan ApprovalC Building.pdfView
  • Building Plan ApprovalD and E Building.pdfView
  • Building Plan ApprovalD and E.pdfView
  • Building Plan ApprovalD and E 2.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter_11zon.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Aurangabad (M Corp.), Aurangabad taluka

Survey, CTS, gat or plot numbers

GUT NO. 08/PART

As published on MahaRERA's project page

GUT NO. 08/PART, NAKSHATRAWADI

Boundaries

North
Land Of Gangasagar Society
South
Land Of Thakur And Then Road
East
Land Of Shriramsundar Naik
West
Land Of Lokmangal Ploting

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAshok Balande—
Chartered accountantYash Nagar—
EngineerAbhay Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology